Customer Day

New wet separation plant NTA 2.0 at Hartsteinwerk Loja

“Today we build tomorrow” was the slogan of the Customer Day held at the Hartsteinwerk Loja on September 23, 2022. A few weeks ago, the new wet separation plant, the so-called NTA 2.0, with a capacity of up to 700 t/h was commissioned there. Crushing and screening technology from Sandvik are among the main equipment of the new plant.

 

Raw material has been mined at the Loja hard stone plant since the beginning of the 20th century. Due to the unique material quality, the extracted raw material is used throughout Austria primarily for high-quality surface layer in road, railroad and airport construction. The hard rock extracted in the open pit by means of drilling and blasting technology is processed in several crushing stages. After the secondary crushing stage was renewed in 2013 and the primary crushing stage in 2015 with processing technology from Sandvik and has proven itself for more than 25 000 operating hours, the construction of the new wet separation plant (NTA) has now been implemented. The foundation stone for this was already laid on November 24, 2020 with the signing of the contract.

 

The joint processing operation, which was developed in a coordination process lasting several months, resulted in a supply contract for a total of three CH840i Hydrocone crushers, a CV217 vertical impact crusher, three SJ screens from the Peak Screening series, and a total of five SP feeders for process support. Construction of the plant began with site creation in October 2020, during which time approximately 450 000 tons of rock were removed from site. Starting in January 2021, preparatory work on the haul-offs (upgrading and expansion to 700 t/h) and the interim storage facility was carried out as part of the winter maintenance of the existing facilities. The solid construction work started in March 2021 and continued until November 2021. Approximately 8500 m³ of reinforced concrete was produced on site and installed by the companies Bernegger and Dywidag. Plant and structural steel erection began in August 2021 in the basement and in September 2021 in the loading area of the plant.

 

Following the departure of the solid construction crews, erection of the main plant was carried out from November 2021 over the challenging Corona winter. Approximately 1000 tons of steel structure, 600 tons of chutes and the plant equipment were erected by June 2022. From January 2022, electrical and piping erection began in parallel with the plant erection. For the new NTA 2.0 with a connected load of 3080 KW, a redundant power supply via the medium voltage level 20 KV was installed. In June 2022, the cold commissioning of all individual units began. In total, around 350 motors, 90 of which can be controlled via frequency converters, were started, adjusted and tested.

 

The first material runs started on 28.07.2022. By September 2022, the plant was shut down and the screening lines and processes were improved to such an extent that the products meet the standard requirements. Since September, the plant has been running regularly at the desired plant capacities. Further optimization processes of the plant are running in parallel with the completion of the assembly in secondary areas. The completion of the completion and further process-technical optimization of the respective required qualities and quantities will still occupy the entire team in the next few months. But here too, all those involved are looking calmly to the future and are sure that, with this very good and professional cooperation, the remaining work will soon be completed. 

 

A total of 90 people came to the Customer Day at Loja in perfect weather. The event was moderated and opened by Mr. Alois Raffelsberger, Sales Manager Austria at Sandvik. After greetings by Mr. Bernegger, the participants were able to follow the development of the Hartsteinwerk Loja Betriebs GmbH and background information on the NTA 2.0 project in two presentations by Dipl.wirt.Ing. Günter Wolfgang Hirsch and DI Stefan Kirnbauer. Following the presentations, the participants then had the opportunity during a plant tour to take a close look at the modern processing plant and to generate their own impression of the technical progress and dimensions.

 

The second part of the day was filled with presentations from Sandvik on current developments in SRP. Jan Martens, Product & Application Specialist for Roller Crusher, gave an insight into the upcoming developments and product innovations in the field of hybrid roller crushers from Sandvik. VP and Head of Digital Solution at Sandvik Rock Processing, Petra Sundström, informed the audience about the current product developments around “SAM – Your Always on Digital Assistant” and made them curious about the future. In particular, the networking of near real-time machine data, e-commerce solutions and a communication platform for interaction between users of the digital service represents interesting digital solutions for a rapidly changing future.

rockprocessing.sandvik

www.bernegger.at

x

Related articles:

Always-on digital assistant SAM by Sandvik improves crushing and screening plant performance

Ever-evolving digital service SAM by Sandvik is designed to support operational excellence in crushing and screening plants. Sandvik is demonstrating how the digital tool can improve customers’...

more
Issue 12/2024 Future-proof expansion

Wolfram invests in a new Sandvik processing plant in Mittersill

The metal tungsten forms the basis for valuable high-tech components in many industries. With its mine in Mittersill, Wolfram Bergbau und Hütten AG operates one of the most important tungsten mining...

more
Issue 10/2018 Diversity

Mason Brothers keep on crushing with Sandvik

P?embrokeshire based Mason Brothers Quarry Products has a longstanding relationship with Sandvik which goes back to the 1990s. The family run company now produces in excess of 100?000 tons of high...

more
Issue 04/2016

Global partnership agreement in crushing and screening

Schenck Process and Sandvik Mining have signed a global partnership agreement. The partnership provides increased crushing circuit productivity for Schenck Process double and single deck high capacity...

more
Issue 07-08/2017

Uncompromising secondary crushing

There is no hiding their enthusiasm when the “decision makers” at Vogelsberger Basaltwerk GmbH & Co. KG, VBW, describe their latest addition. The optimally designed Sandvik CS550 installed at the...

more