WEIR Minerals’ process-focused solution ups CNC output

Stilfontein-based sand and aggregate supplier CNC Crushers raised throughput at its Roadstone Shaft 5 crushing plant by 45 % while cutting back on maintenance and simultaneously increasing production, after implementing a full process-focused solution from Weir Minerals.

According to JD Singleton, Weir Minerals General Manager for Trio® and Enduron® equipment, the customer was experiencing high wear on the installed conventional cyclone, as well as on the older technology pump, having to replace liners every 120 hours of operation. “Our brief was to increase solids to the cyclone underflow and increase the wear life on the cyclone feed pump,” says Singleton. “The continuous breakdowns experienced with the older-technology crushing equipment, and the excessive oil usage was also causing high downtime for the plant.” As a solution, Weir Minerals installed a new technology Warman®WBH®100 slurry pump and a Cavex® 400CVX10 hydrocyclone; it also replaced the existing cone crushers with Trio® TC51S and TC36SH cone crushers to increase up-time and reduce maintenance costs.

“After 1900 operating hours, the slurry pump was still running without needing any replacement parts, a vast improvement on the previous mean time between liner replacements of 120 hours,” Singleton says. According to CNC owner Carl Crous, this has meant that the company could take pumps off the critical maintenance list.

With regard to the hydrocyclones, these proved to be more efficient than the conventional hydrocyclones, highlighting the benefits of the Cavex® hydrocyclone’s laminar spiral inlet geometry. “The Cavex hydrocyclone increased the mass pull to the underflow, which resulted in increased production and reduced slimes to the tailings dam,” he says. For their part, the cone crushers increased plant availability as well as production, while meeting the criteria of matching the customer’s existing footprint. These crushers also incorporate multiple hydraulic cylinder clamping and adjustment, which enabled them to reduce the closed-side setting adjustment time from an hour and a half to just 5 minutes. In addition, their larger socket assembly was able to give full support under both extreme and light load conditions, providing a longer service life. After the cone crushers were installed, a spares and service agreement was put in place to maintain maximum plant availability.

Following the crusher upgrade, a competitor’s installed primary and tertiary classification screens were replaced with a Trio® TIO5162 (5’ x 16’ double deck) inclined screen, and the final product screen was replaced by a Trio® 4102 (4’ x 10’ double deck) inclined screen.

www.minerals.weir

x

Related articles:

Weir Minerals enhances pump maintenance with adjustment technology

With a longstanding reputation for engineering expertise, Weir Minerals continually develops solutions and technology to better serve the mining industry. Recognising that throatbush wear rate has a...

more

Weir Minerals

Weir Minerals are specialists in designing, manufacturing, delivering and supporting critical process equipment solutions including pumps, hydrocyclones, valves, comminution equipment, rubber and...

more
Issue 07-08/2015

Fitting solutions from Weir and Trio

With Weir Minerals acquiring Trio Engineered Products, customers are benefitting from the convenience of sourcing complete solutions from a single supplier (Fig.). The combination of the Trio®...

more

Weir Minerals expands product line

Weir Minerals announced three new additions to its industry-leading Lewis® range of pumps and valves for the sulphur, sulphuric and phosphoric acid industries. The new Lewis® VL Axial Pump, Lewis®...

more

Weir Minerals Total Asset Management Plan for increased productivity and significant savings

Weir Minerals have further strengthened their partnership with Tronox by entering into an exclusive arrangement to take ownership of the maintenance, asset management and optimisation of the mine’s...

more