ABB completed completed commissioning of two synchronous condensers and harmonic filters for Xstrata Copper’s Antapaccay project in the Yauri district of Espinar Province in southern Peru. The open-pit mine and processing operation are located approximately ten kilometers from Xstrata’s Tintaya mine at 4100 m above sea level. The plant has an estimated process capacity of 70 000 t/d for the first half of 2013 and is projected to produce an initial 160 000 t of copper in concentrate per year including significant gold and silver by-products.

ABB’s scope of supply included harmonic filters and controller, two brushless synchronous condenser systems comprised of 20-megavolt ampere synchronous motors, distribution transformers, frequency converters, excitation and protection panels as well as chiller systems.

The project is located in a remote area and is connected by a long power transmission line. ABB’s synchronous condensers will ensure accurate and dynamic power factor compensation for safe and reliable mine operation at this remote location. By integrating synchronous condensers and harmonic filters the harmonics are mitigated and short circuit levels improved, thus optimizing Antapaccay’s productivity and energy efficiency.

ABB’s expertise in the integration of harmonic filter systems with synchronous condensers, strong local service presence and an excellent reputation in the South American market, were important factors for winning the contract with Xstrata. Bechtel, Xstrata’s EPCM contractor, managed the overall project. ABB has also supplied two identical synchronous condensers for Xstrata Copper’s Las Bambas project in Peru, with commissioning scheduled for the fourth quarter of 2014.

www.abb.com

Related articles:

Issue 10/2012

ABB to increase network power quality

ABB was recently contracted to supply two synchronous condensers for Xstrata Copper’s Las Bambas greenfield copper project in southern Peru. The contract was awarded in the second quarter of 2012,...

more
Issue 10/2011

New ore hoisting system for Xstrata Copper in Australia

ABB, one of the leading power and automation technology groups, recently won an $11 million order to supply a complete ore hoisting solution for Xstrata Copper’s Ernest Henry Mining (EHM)...

more
Issue 01-02/2013

Gearless drive system for ThyssenKrupp overland conveyor system in Peru

The Siemens Drive Technologies Division has received an order from ThyssenKrupp Robins (Greenwood Village, Colorado, USA) to supply the gearless drive system for the overland conveyor system in the...

more
Issue 07-08/2019 Improved reliability and efficiency

thyssenkrupp to deliver conveyor systems for new copper mine in Peru

O?ne of the world‘s largest copper reserves will soon be accessed with the help of high-capacity overland conveyors from thyssenkrupp. The Industrial Solutions business area recently won a contract...

more
Issue 05/2013

Siemens to equip copper mine in Peru

Hudbay S.A.C Peru, a subsidiary of Canadian Hudbay Minerals, has ordered tech-nical equipment from Siemens for the power supply and integrated automation at its Constancia copper mine in Peru. The...

more