Profitable overburden

Generating profits from quarry waste with technology from CDE

CDE has supplied a 250 t/h plant for the Swedish firm Swerock in its bid to recover sand and aggregates from quarry overburden to use in its own concrete business. Part of the Peab-Group, Swerock is one of Sweden’s largest suppliers of materials and services to the construction industry. The company provides services across the Nordic region including supplying concrete, gravel and rock materials, transport and construction machinery as well as environmental services such as recycling, soil remediation and water treatment.

 

CDE and Swerock have a long-standing relationship, with CDE having installed Swerock’s first project back in 2005 at its Blentarp site. Commenting on the decision to work with CDE again, Christian Lindgren, Operations Manager for Swerock, said: “Having worked with CDE for many years, we knew that they could deliver a plant to meet our specific requirements. As this plant represents a significant investment, and as one of the first to supply this type of material for concrete production in Sweden, we wanted to make sure it is capable of meeting our needs.”

 

One of the greatest concerns that Swerock wished to address was the amount of quarry waste that the firm was producing. Quarry waste can be a challenge for operators across Scandinavia and wider Europe as it can lead to surplus stockpiles, which can block access to reserves and take up valuable space, as well as being costly to store or dump. Swerock sought to overcome this challenge by consulting wet processing experts CDE to design and install a plant that could process large amounts of overburden, also known as moraine, a by-product of quarry operations. This is not only to reduce costs and stockpile storage, but also to produce material which can be repurposed into the industry to help reduce waste and maximise resources.

 

The ability to recycle is particularly important at present with the material shortage in Sweden, so therefore the new investment contributes to both Swerock’s sustainability and self-reliance goals. The investment in technology to respond to this specific problem solidifies Swerock’s commitment to producing in-spec concrete to be used in-house in its concrete division. It is also allowing the firm better adapt production to customers’ needs.

 

The new plant at Swerock’s site in Blentarp processes feed material at a rate of 250 t/h to reduce the organics content in the output. It comprises of CDE’s R4500 primary feeding and scalping screening system, M4500 modular wash plant to pre-screen the material with two integrated counter flow classification units (CFCU) density and sizing classification systems, AggMax™ scrubbing and classification system, EvoWash™ sand wash system, AquaCycle™ thickener and organics static screen.

 

Swerock requires a very specific sand output, 0 – 2 mm, with tight specifications which leaves little room for error as this is an important component in concrete production and replaces the natural gravel. The variable particle size distribution (PSD) of the feed material was a major challenge in ensuring an in-spec 0 – 2 mm fraction output.

 

This solution has two CFCU density and sizing classification systems to increase the separation surface area and increase organics removal. All the fine sand removed in the CFCUs is captured and dewatered as a fine sand product through the additional EvoWash and stockpiled. To provide the best opportunity of achieving the gradation required, the CFCUs are used directly after the cyclones. The cyclones perform the primary removal of the -63 μm with the overflow from the cyclone going to the AquaCycle. The cyclone underflow passes directly into the CFCUs where a variable rising current of water and a fluidised sand bed impact on the amount of fine sand removed, which is generally up to 0.250 mm.

 

CDE introduced the ability to further remove some of the 0.250 mm material after the CFCU which can be either discharged away from the 0 – 2 mm washed sand or proportionally reintroduced to it to nurture the 0 – 2 mm grading according to the requirement. The CFCU will continue to smooth out the variability of the incoming material to ensure a much more consistent output sand whilst also removing the lightweight organic material.

 

The use of a unique corrective solution eliminated any concerns around removing too much sand at the bottom end of the sand curve, giving more control over the gradation of the final sand product, and allowing for adjustment to ensure the required specification is met while providing flexibility to produce other specifications if desired.

 

To deal with the concerns of lignite and organics throughout the feed material, CDE has incorporated an AggMax to the solution. The AggMax has an integrated trash screen which allows for the effective removal of organics and other lightweight contaminants, ensuring the production of the highest quality final aggregates. Finally, the static screen on the recycled water circuit also suits the overburden feed material as it catches a lot of the lightweight, floatable materials that the cyclones carry to the AquaCycle. Over time these materials can saturate and become suspended in the water which can lead to blocked spray nozzles. The static screen reduces the potential of this happening.

 

The plant allows Swerock to produce 7 products; the 0 – 2 mm used in concrete production, two additional sand fractions in 0 – 0.250 mm and 2 – 4 mm, 4 aggregate fractions in 4 – 16 mm, 16 – 32 mm, 32 – 100 mm and +100 mm used for a variety of construction and infrastructure projects.

 

Christian Lindgren says the new plant is allowing them to produce a highly specific, quality sand contributing to self-sufficiency: “We are really focused on becoming more sustainable and reducing our carbon footprint, and it’s technology like this that is driving us towards our goals. This plant is allowing us to enhance other business divisions internally, so we can focus on our commitment to become more sustainable and offering more durable products of consistent quality to our customers, whilst also allowing us to reduce the amount of quarry waste that we’re stockpiling and refine products from surplus material.

 

CDE’s Head of Business Development for Europe, Eunan Kelly, comments that it’s plants like these that are the ones of the future. “It’s been a pleasure to work once again with Swerock. Over the years we’ve nurtured and developed a fruitful relationship, and we’re delighted that they chose to partner with us on this project.”

www.cdegroup.com
x

Related articles:

Issue 07-08/2024 Reappraise waste by-products

Waste stockpiles: the key to unlocking full potential of a raw material extraction operation

As the rate of global resource extraction continues to accelerate, finite natural materials continue to deplete, and barriers to gain approval for new mineral extraction sites mount, CDE, one of the...

more
Issue 09/2016

New CDE washing plant for construction & demolition waste recycling in Norway

Recently Velde Pukk and CDE held a three-day demonstration event at Sandnes near Stavanger/Norway, to present the new wet processing plant with a capacity of 300 t/h for construction and demolition...

more

CDE

CDE get ready for a new product launch. On 25th June we look forward to debuting our most efficient water management solution to date, a solution that promises greater functionality, improved...

more
Issue 09/2013

CDE plant upgrades

For over 20 years, JPE Holdings Ltd has grown to develop its business of supplying aggregates, groundworks and site clearance, becoming one of the Midland’s leading suppliers to the construction...

more
Issue 03/2014

Silica sand washing plant for Tooperang Quarry

Tooperang Quarry has announced the completion of a silica sand washing plant at a new site near Adelaide/South Australia (Fig. 1). The plant has been supplied by CDE and is producing glass sands for...

more